The Project Manager's
Corner: The Past as Precursor
Gary Sanders, TMT Project Manager
January 2006
I want to start 2006 by introducing a monthly column by the
TMT Project Manager. My goal is to give you a chance to watch
the hectic "going's on" of a project as intense and
exciting as TMT. I will pick a highlight each month that is
a good story, but also one that signals what we are doing and
where we are heading.
I will be a bit more long-winded this month as I tell you of
our founding steps in the past two years.
TMT began as a project in June 2003 when the leaders of our
three precursor projects (AURA's Giant Segmented Mirror Telescope,
ACURA’s Very
Large Optical Telescope and CELT's California Extremely
Large Telescope) agreed to join the NSF's publicly funded efforts
with the traditionally private funded community represented
by Caltech and UC. And Canada weighed in with its support and
commitment as well, completing the troika.
This was a remarkable move, spanning very different groups
in the traditional landscape of astronomy. It was recommended
by the U.S. National Academy of Science's most recent decadal
survey of astronomy, issued in 2001, the report that identified
a thirty meter-class telescope as the highest ground-based astronomy
priority for the next decade. The report recognized the high
cost and enormous challenge of such an undertaking and called
for a joining of public and private astronomy institutions as
the best way to marshal the needed resources and talent… but
whether anybody would accept the advice was an open question.
The new TMT partners set out to form a centralized project
office in Pasadena. I joined TMT in April 2004 fresh from the
construction of the Laser Interferometer Gravitational Wave
Observatory (LIGO), the first major facility capable of detecting
gravity waves from deep space. I was ready for another big challenge.
My early focus was working with the partner teams to create
an effective organizational structure, and directing a trade
study of the three precursor designs to select the single, unified
TMT reference design.
This was aided immeasurably by a Science Requirements Document
delivered by the TMT Science Advisory Committee and Jerry Nelson,
the TMT Project Scientist and veteran of the design of the Keck
telescopes on Mauna Kea. This valuable document gave us a science-capability
target to structure our design studies toward.
A vigorous "16-week study" that took about 18 weeks
in reality culminated in the reference design described elsewhere
on these Web pages. It was adopted by the project and blessed
by the TMT Board in October 2004.
Our focus turned next to the suite of scientific instruments
proposed for the TMT, and their associated adaptive optics systems.
Again, our venerable Science Requirements document guided us,
and by mid-November 2004, the project was able to adopt an architecture
for adaptive optics and science instruments that were designed
to take best advantage of the unprecedented number of photons
gathered by the vast primary mirror.
The year 2004 finished with key meetings between the project
and the industrial firms who have built all of the world’s large
commercial telescope mirrors. Our goal was to establish a design
for the crucial TMT primary mirror segments that could be produced
by industry with a very low cost target for each segment. The
two Keck telescopes produced 84 similar segments, including
the ones in the telescopes and spares. TMT's comparable number
is a superficially imposing 860 segments. We knew that we had
to learn, guided by industry, how to make these cheaply and
as fast and as good as we need them. This is a job for industrial
capabilities, not professors on university campuses. We had
numerous face-to-face meetings and spent the 2004 holiday season
writing the first bid documents for these mirrors. (Is there
a message here? I am writing this during the 2005 holidays!)
The pursuit of our total optical system continued in January
2005 in meetings with industrial suppliers of deformable mirrors,
another key component of TMT. Many science applications of the
TMT demand a light beam corrected by adaptive optics, and so
are very dependent on the ability of these deformable mirrors
to deftly change shape in the precise way to cancel the shimmering
of Earth’s atmosphere.
TMT issued formal Requests for Information, followed by Requests
for Proposals, to all of these suppliers. These led to bidding
and signed contracts by the spring. This was the beginning of
the large scale industrialization of TMT.
Today, the design and prototype studies set in motion at the
beginning of 2005 are yielding design reports and prototype
mirrors, with cost estimates for the future, in time for the
TMT Conceptual Design Review in May 2006.
The TMT Instruments program was kicked off in February 2005
with release of Requests for Proposals to all significant astronomy
instrumentation groups in North America. Our Science Requirements
Document gave us good definitions of the instrument features
needed for TMT. But the best ideas for obtaining these measurements
often come from the specialized groups in astronomy known for
clever instrument designs.
TMT reached out in an open competition to groups within the
partnership and across the broader community, offering to support
initial instrument design studies. For our eight envisioned
instruments, TMT received interested responses from 41 groups.
These resulted in subsequent mergers and 16 formal proposals.
After extensive peer review, some shuffling and negotiating,
a dozen teams are studying the various TMT instruments and their
associated adaptive optics systems. Our ongoing dialogues with
these groups show that early in 2006, as scheduled, we will
be receiving some very good, and innovative, instrument designs.
Our focus turned inward in March toward design work within
our team and to planning out the entire design process. Work
began on other optics, the telescope enclosure, adaptive optics
models and a myriad of related design efforts. A marathon visit
to the candidate sites for TMT in Chile and completion of the
Mauna Kea site testing permit process signaled a push onto more
mountainous terrain—it was easy to dream about a TMT on any
of them.
Permission to test the conditions above Mauna Kea was received
in April 2005, and mobilization began. Preparation also began
on one additional mountain in Chile.
The telescope structure design kicked off in May, as did the
design of the crucial segment assembly support units for the
primary mirror. We require 860 of these units to support, sense,
and move the 860 mirror segments (740 in service at any one
time plus spares) and so, again seeking cost efficiency; these
are being designed with industry.
The primary mirror control system design was initiated in June.
A comprehensive site testing workshop was held with representatives
of other large telescope design teams. Adaptive optics modeling
received a great deal of attention.
The primary mirror alignment and phasing system design started
in July. Those 740 mirror segments must act like one beautiful
mirror. This is the system that will make that possible with
a push of a button. Our team is the same team that did this
wizardry for Keck and showed it could be done.
As August began, four of six candidate mountain sites for TMT
had operating robotic observatories collecting data at night.
Preparation for the fifth was underway. Requirements for the
buildings on the summit and for lower altitude support facilities
were aired for the first time. All designs were proceeding apace.
The project came together as a whole in September and saw itself!
The month was marked by a big week long "TMT
Week" held at the Aspen Center for Physics Ninety scientists
and engineers attended, and every part of the TMT effort was
presented for discussion, including the work of our instrument
partners.
Though we all knew intellectually that work was brisk everywhere,
no amount of multi-point videoconferences is as effective as
being together face-to-face. Those grainy, jerky backlit faces
in all of our daily and weekly review videocons in checkerboard
patterns on a TV screen, one head talking after another with
electronic slides scrolling across another screen, gave way
to a room full of colleagues peppering each other with questions
and opining about the really thorny issues. The week went fast
and, alas, we left with an even longer list of action items
and things to check. September 2005 will be remembered as when
the TMT all came together.
With all of the designs progressing, work began in October
on formal "bottom-up" cost estimating. No, this stuff
won’t be free and the best TMT that we can design is the one
we can afford. “Designing-to-cost” is the new mantra. First,
we need to get through the sticker-shocks that await us!
The fifth in our set of six mountains came alive in November
as the first robotic telescope observations begin on another
Chilean peak. Permissions are requested for the sixth and final
test site, also in Chile. Designs and planning for the May 2006
Conceptual Design Review loom on the horizon.
Finally, in December, after some debate, we
adopted an innovative calotte concept for the TMT enclosure,
yielding a cost-effective and technically superior housing
for the TMT and all its complex systems. Now we are starting
to look at the design of related summit facilities. It feels
more real every day.
These are just tidbits. We are moving forward every day, and
our accomplishments and emerging challenges during the mountain
of effort ahead should make interesting reading.
Stay tuned to this web space for monthly updates on this grand
and unique venture. |