The Project Manager’s
Corner: How Much Will TMT Cost?
Gary Sanders, TMT Project Manager
August 2006
We are working on the answer to this important question. Very
hard. Price quotations arrive every day. New requirements documents
and requests for quotes go out, as well, every day. Cost-estimating
tally sheets, with narrative descriptions of the design and
estimating method, are stacking up. A data base is filling.
Some items are coming out higher than expected; others leave
a bit of room within our expectations.
Later this year we will have laid out a detailed cost estimate,
and outside experts will pore through it and render an opinion
on what has been left out, or what’s been judged with too much
optimism or—perhaps—too conservatively. We will refine some
things and then we will have a basis for planning adjustments
to what’s included in the TMT design, and how the project can
be carried out within budget.
We have all heard of those megaprojects that turn out to cost
much more than originally stated. The tunnels in big cities
or under the English Channel, or the Superconducting Super Collider,
or even just that freeway through town, all described in the
newspapers to be 2 or 3 or 4 times the original cost. How can
that happen? Are there reliable methods to estimate and plan
the costs of big, one-of-kind projects? Do the methods that
apply to airports and bridges also apply to big science projects?
The first thing to ask: how can such large overruns happen?
Generally, it is due to changing the project requirements or
its design in midstream. Politics, changing customer desires,
or lack of focus on building what was agreed upon are invitations
to cost growth. The costs change because the project has been
changed. But even if you stick to the original project, there
is risk. There are, however, methods to prepare a cost estimate
and to plan for those risks.
There are many reliable methods that can point to reasonably
accurate costs. There are also methods to keep on track to work
within those costs as the project is carried out. Farther on,
we will describe some of these methods and how we are going
about this in TMT.
Airports and cruise ships and airliners and big shopping centers
and major bridges and tunnels are all quite risky, and they
tend to be one-of-a-kind projects. Experience with previous
projects provides only a rough guide to the current project.
Requirements and circumstances and design solutions are often
sufficiently different to limit past experience as a reliable
guide.
Science projects seem to be even more challenging and therefore
more risky. They often involve new technologies and new materials,
and even outright inventions in the common sense of the word.
We scientists like to think that what we do is so special that
the methods used on those “conventional” projects in the previous
paragraph cannot fully apply. But this is not true.
As challenging as TMT is, a new generation of cruise ships,
or the English Channel tunnel, or that 169+ story skyscraper
in Dubai are just as novel and risky. Cost risks can be treated
in the same way in TMT as in those projects. The best practices
used in these megaprojects apply to TMT.
There are several ways to estimate project costs. Generally,
the first estimates are done by finding out all of the costs
of the most closely related projects, and estimating the new
project costs item-by-item or subsystem-by-subsystem. To use
a specific analogy: we know the costs of the Keck and Gemini
telescope mirrors. Can’t we just scale those costs by part count
or mirror area or pounds of glass or some such parameter? Can’t
we do that for every part of TMT that has an analog in those
projects? TMT might even use similar designs and the same suppliers.
We can do that and we would learn a great deal. But this technique
will not capture the cost of all of the project risks and the
cost impact of significant differences in requirements. TMT
mirror segments are more aspheric. They are different in size.
We may have little guidance whether we can polish twice as fast
if two or more segments can go on the same machines, compared
to the larger Keck segments. Or the steeper curvature may make
the polishing and testing much more laborious. Making 740 segments
for TMT, instead of Keck’s 36 segments, means we have a big
chance to take advantage of the savings from “almost mass production”.
Concrete and steel prices have zoomed upward in the last few
years across the globe. Though Keck and Gemini were built only
a decade ago, the world market in commodities, energy, labor,
and transport are dramatically different. TMT may ship about
5,000 tons of fabricated steel elements across oceans to its
site. Ocean freight is a brave new world.
Analogies to the past and parametric scaling, though quite
useful, leave too much uncertainty. We have to do the estimate
for TMT in excruciating detail, using what is called a “bottom-up”
estimate.
Every piece of work in the design and fabrication and assembly
and testing of TMT must be collected in a giant list, organized
according to all of the delivered pieces of TMT. This list is
called a Work Breakdown Structure (WBS). Having done a conceptual
design of TMT, we know what most of the deliverable elements
of TMT are. And we know the steps to deliver each.
We prepare a table with a tree-branch structure (a list of
lists) with the TMT as a whole at the top. The main branches
of this tree are the main subsystems (summit facilities, enclosure,
telescope, adaptive optics, the instruments, and so on…). Each
main branch has smaller branches representing the delivered
sub-subsystems or components. The tree diagram is
worked down to as many as nine levels of branches.
Every piece of work or item to be delivered in order to build
TMT is represented. Right now, this WBS, including all project
phases and items, fills more than 700 pages. The lowest-level
pages in this tree structure describe the estimate for delivering
a single item in the WBS, including needed labor, purchased
items, contracted fabrication, travel and a tabulation of cost,
schedule and technical risks for that item. The complete tree-structured
estimate is captured in a big database.
The engineer or scientist responsible for each of the main
or mid-level branches in the estimate is responsible to prepare
the estimate for all of their deliverable items or tasks. They
generate the estimate at the lowest level in this tree of lists.
This is called “bottom-up” estimating.
All of the estimates are added up to produce the larger delivered
and testable items. Science instruments, primary mirrors, the
telescope structure, the secondary mirror assembly, and the
top-level observatory software are all deliverable items. When
combined, they become TMT.
As the cost estimate is rolled up, project designers can consider
ways to reduce costs or to eliminate items or—perhaps—to add
some feature to TMT thought to be out of reach. This is part
of designing-to-cost. And it is the opening round of staying
on budget.
As project manager, I look forward to that night on the mountain
when the first starlight will fall on the giant mirror and the
very first inkling of new science will be revealed. But, in
the back of my mind, I know that I will also be thinking of
how we stayed on budget. |