The Project Manager’s
Corner: A Great Year
Gary Sanders, TMT Project Manager
December 2006
I am sitting in a lounge at Vancouver airport thinking back
over a great year for TMT. I'm returning to Pasadena after a
very successful meeting of our Science Advisory Committee (SAC),
described elsewhere in this issue by our SAC Chair, Paul Hickson
of University of British Columbia. That meeting capped this
great year.
Last January I began my series of Project Manager’s Corners.
This has been my personal attempt, each month, to help you follow
TMT openly and as it progresses. I began in January by looking
back to the origins of the project, and I reported on our search
for a mountain site, our science instruments, our tiniest and
most challenging mirror. I described a major project milestone,
our Conceptual Design Review.
In June, TMT took its public outreach up a notch and initiated
our series of monthly Newscasts.
In the Newscasts, I continued my Project Manager's Corners,
adding to the other regular features in the Newscast. In successive
months, I described the Newscast, how our Board represents the
segments of the involved astronomy community, how we estimated
the cost of implementing our full Conceptual Design into an
observatory, how TMT is an example of a large science project
that others can learn from, and how telescope designers must
anticipate nature's challenges such as earthquakes. We finish
the year by combining our November and December issues into
a year-end edition. This is a good time to look back and take
stock.
Following the successful Conceptual Design Review, our team
carried out a very detailed cost-estimating exercise. Our estimate
included our full initial Conceptual Design scope and it was
reviewed by a distinguished external panel that confirmed the
quality of the estimate. Flush with success, we confronted one
significant problem. Our estimated costs exceeded the TMT Board
target cost. In my August Project Manager's Corner, I mentioned
the all-too-common process of refining the scope of a design
once the costs are understood.
Armed with our favorably reviewed estimate, we possessed the
tools to carry out a value-engineering exercise. We reviewed
the project scope in light of the costs and made some design
changes, eliminated some facility spaces, tightened up our enclosure
dimensions, and left the key elements of the design that deliver
science essentially untouched. Our estimate is now close to
the Board target of $700 million (in 2005 dollars), with some
final scope options and implementation details to be considered
by the TMT Board in January.
Our site-testing program is collecting good data on five candidate
sites. We have met with host governments and institutions associated
with each of these sites. TMT should be able to select a site
on our planned schedule in 2008.
Adaptive optics, and telescope design and development, have
made great strides and the next phase of the development for
these subsystems is to be initiated after the January Board
meeting.
With reviewed designs and an efficient model for construction
costs, much attention has been paid to how TMT will be operated,
which instruments are to be provided at first light, and how
the greater instrument suite will be implemented following first
light. We have learned a great deal from discussions with the
staffs at the Keck, Gemini and VLT observatories, and we thank
them for their valuable advice. The product of these science
operations/instrument development discussions was brought back
to our own community in the SAC meeting just completed. The
SAC provided positive feedback on these plans.
The SAC meeting and the upcoming Board meeting wrap up this
great year of 2006. And they are points of departure for the
mature development tasks and work toward our Preliminary Design
Review, site selection and plans for the next phase of TMT implementation.
Our world class TMT team, having worked so hard, will have
an interesting year in 2007. |