The Project Manager's
Corner: Scheduling TMT I
Gary Sanders, TMT Project Manager
February 2007
Last month I discussed adjustments to the design of TMT and
to its estimated cost. I described our progress into the last
phase of TMT design. By May 2008 we plan to complete the site-independent
Preliminary Design of TMT. This means that we will have fully
defined the design that we intend to build and that this design
can be shown to meet the design requirements. Following that
phase, we will have selected the TMT site and will proceed to
complete site-specific elements of the design, such as different
foundations for different local geology. Final design, where
detailed construction documents are completed for industry,
follows and this initiates construction.
One of the important elements of this process is defining the
complete schedule to construct TMT.
How does a big project like TMT go about this?
The simplest schedules are an ordered list of tasks with each
assigned an estimated time to complete. Such schedules are commonly
shown as a list or a chart of time bars on a graph that looks
like a waterfall of bars scrolling down the list and marching
out in time. The figure displays such a schedule as a cartoon.
This is a good way to start organizing early thoughts. But it
is far too simplistic for a big project.
Some tasks must wait till other tasks are fully completed.
Some may progress in parallel. Some may wait for several other
tasks to be completed. Some represent parts of the project that
if delayed will delay the entire project. These are called critical
tasks. Others can take place whenever there is time for them
within broad limits. Delaying these does not stretch out the
entire project. Some tasks can be made to progress more quickly
than planned, for example by using more shifts per day, or weekends,
for production tasks. Others depend upon a unique resource or
method and cannot be hastened. Buying and receiving a large
ingot of a specialty glass may simply not be speeded if there
is only one supplier with one oven and one process able to meet
the requirement.
A project like TMT may have thousands or tens of thousands
of tasks in the final schedule. What do you need to design such
a schedule?
First, the plan must be made for each major subsystem by experienced
designers of such systems. These designers must have real technical
expertise for the tasks planned and they must have actually
carried out similar projects before. This enables realism in
the schedule design and the strategy. It is best when these
experts are the actual team members responsible for carrying
out the schedule. They will then be working to their own plan.
This is schedule ownership.
The second required element is hinted in my reference to each
subsystem. This implies an organization of the work into parallel,
meaningful subprojects that come together into the entire project.
Each of these is a delivered item. Delivering all of these items
leads to delivering the entire project. This way of organizing
the entire work of a project into all deliverable items and
tasks is called a Work Breakdown Structure or WBS. The WBS defines
how the cost estimate is tabulated, how the schedule is made
up of tasks and how the work will be managed.
The third required element is the overall architecture of the
work plan and any imposed constraints. Tasks cannot begin before
funds are available, for example. The project may be required
to be completed before some external milestone date. This architecture
and top level set of milestones are adopted as guidance at the
beginning of the schedule planning.
Next month I will describe the remaining steps in building
the typical large project schedule and discuss our vision of
how TMT will be implemented in time. |