Timeline

JUN
6
2019
Enclosure Pre-ship review

6d2b153da96f4d71b905ab3a8180496a76280310

Enclosure is completed and ready to be shipped from Canada.

JUN
25
2020
Fixed enclosure base structure complete

Af2bb07588652298fcc4ce0e1de9de605784c8b6

Enclosure base is complete and ready to accept the upper part of the dome.

JUN
26
2020
Enclosure installation begins on site

F9fa6aaa33e8abdee92ca5cde2d9832d248024f1

The telescope enclosure started to be installed on the its base at the TMT site.

JAN
27
2021
M2 cleaning system ready to ship to the observatory

93a85a73c90cd863c06c83e287dc7c036fb69a18

M2 cleaning system ready to ship to the observatory

FEB
1
2021
M1 coating chamber built

3418932e8fcf19eafe8bb10899f3416751b31eca

The coating chamber is built and ready to ship to the observatory

MAR
24
2021
Telescope structure fabrication completed

03b444599dad453b7cfeb7f4fe9f0cd851ec52c8

The fabrication of the telescope structure is completed in Japan and ready to ship to the observatory

MAY
27
2021
All M1 segment blanks are fabricated

Fb263a6a01be56be0b33ec58ac36e51576f002ae

The last segment blank is completed and sent for polishing

JUN
17
2021
M3 cleaning system ready to ship to the observatory

Da493847bab993ce931135093503a8d28de1db97

M3 cleaning system ready to ship to the observatory

JAN
3
2022
M2/M3 coating chamber built

C1328804db5e10fb1349d5d0708f7b2653260d33

The coating chamber for the secondary and tertiary mirrors is ready to be shipped to the observatory

FEB
25
2022
Enclosure Shell Complete

0ce455070b9dc0ce4b58f759ca3464c98caaf114

The Observatory Enclosure is built on site.

SEP
9
2022
M2 is completed

Fb1f5f88b00b24f5d19705b49316878dfe61c83e

The secondary mirror is built and sent to the observatory

SEP
23
2022
M1 cleaning system ready to ship to the observatory

18fb5da89407f86ab33642836f7ef27951d2d092

M1 cleaning system ready to ship to the observatory

JAN
25
2023
M1 control system (M1CS) built

Cc886953871f66e043c47ad80f8a42949ef884a2

The control system for the primary mirror is built and ready for integration

SEP
27
2023
Permanent power available on site

Power is generated on site and in its final form.

NOV
22
2023
Summit facility building complete

2d2d1819c5974bf258b3429144482509a24caca6

The Observatory facility building is complete.

FEB
12
2024
M1 phasing system (APS) built

A09f0aef8c595777f8490da04ab34aa7162b1be1

The phasing system for the primary mirror is completed and ready for shipment to the observatory

MAR
19
2024
M3 is completed

Fb48872a49c9f92c5b353d767ed8cac7a0c4d424

The tertiary mirror is built and ready to be shipped to the observatory.

DEC
23
2024
M1 segment polishing is complete

188f60c47b5d657eb81dbd525682705f8efced76

The last segment is polished and sent off for ion beam figuring

JUN
19
2025
M1 phasing system (APS) ready for first light

47202796b64bcc5c169c0758b0f91bf4a88e65b7

The primary mirror phasing system is fully integrated to the observatory and ready for operations.

OCT
2
2025
Primary Mirror on-sky test (Phase A)

First on sky test using 40 segments at prime focus completed

FEB
17
2026
Primary mirror on-sky test (phase B)

First on sky test using 40 segments at Nasmyth focus completed

MAR
27
2026
M1 segment ion beam figuring completed

551136a968f85fe05fea8ec4f55b9f12845b13a9

The last segment is fully ready and ready to be integrated to its control system.

OCT
6
2026
Primary mirror on-sky test (phase C)

Primary mirror with 492 segments aligned and phased on sky with APS, M2 and M3

JUL
20
2027
First light complete, ready for science

Observatory is completed and ready for science!!